In the Voss biogas plant construction site in beautiful Norway, the teams of the purchaser BIR AS, process EPC-contractor Biovoima, civil work contractor LAB Entreprenør AS – a company within the AF Gruppen, and all the biggest subcontractors joined their forces in a common workshop early this week.

Workshop consisted of hard work in order to clarify all open design interfaces and create a plan for synchronization of work packages, yet also excellent team spirit creation in forms of construction site “olympic games” and evening activities.

“It’s such a great feeling in this project that everyone is working together towards a common goal, sitting on the same side of the table. I can be nothing but happy for the ways how BIR and LAB are used to working; I think it also suits our company culture very well”, rejoices Tero Kemppi, the project manager from Biovoima.

Excavation works of the plant have started last week and concrete works will start within a few weeks. Biovoima will start their site works from underground process pipe installations in August-September 2024.

More information:

Tero Kemppi

Project manager, Suomen Biovoima Oy

+358 50 408 7100